News & Update Bulletin #5

March 12, 2018 | Headlines

COLUMBIA ST FOUNDATIONS : Excavation for the basement and most of the foundations are completed.

MASS AVE FOUNDATIONS : The slurry walls are completed and excavation for the 2-story garage started in the last week in February.

47 BISHOP ALLEN DRIVE : The slab was poured in late February, followed by erecting the first floor framing with prefabricated wood panels.

PLANNING BOARD HEARING : The 3/20 hearing is a request for the Planning Board to grant one additional approval so the full parking lot at 65 Bishop Allen Drive can be used as intended and previously approved by the Planning Board.

See link to website newsletter →